Development of business units

Development of order book

Awarded transport contracts

Transport contracts awarded
(rail) — H 1 2021

Term

Volume
(million train-path km)

p. a. 1)

total 1)

 

Czech Republic

MoT Trains (R14)

12/2022—12/2027

1.7

8.5

Sweden

E20 Train
Roslagsbanan 2)

06/2021—12/2021

3.2

1.6

Total 1)

  

4.9

10.1

1) Differences due to rounding are possible.
2) Extension of existing contract.

Transport contracts awarded
(bus) — H 1 2021

Term

Volume
(million bus km)

p. a. 1)

total 1)

 

United Kingdom

London
(17 separate lines) 2)

2— 5 years

17.5

41.4

Hungary

BKK A7+BKK A8 3)

2 years

11.2

22.4

Czech Republic

City of Trinec

01/2022—12/2031

1.2

12.0

Slovakia

City of Trnava

06/2021—05/2031

1.2

11.6

Sweden

E20 Bus Norrort 3)

06/2021—12/2021

17.2

8.6

Sweden

Kristianstad

12/2022—12/2023

3.5

3.5

Serbia

Leoni passenger transport 3)

02/2021—01/2022

2.6

2.6

Serbia

City of Kragujevac 3)

07/2021—07/2022

2.4

2.4

Slovakia

City of Komarno

07/2021—06/2031

0.2

1.8

Other 1), 2)

 

0— 4 years

1.5

2.2

Total

  

58.5

108.5

1) Differences due to rounding are possible.
2) Including extensions of existing contracts.
3) Extension of the existing contract.

Major commissionings

Major commissionings
(rail) — 2020/H 1 2021 1)

Term

Million
train-path
km p. a.

thereof
versus
H 1 2020

 

Czech Republic

MoT (R14)

12/2020—12/2027

1.7

+0.9

Total 2)

  

1.7

+0.9

1) Services were previously not provided by DB Arriva.
2) Differences due to rounding are possible.

Major commissionings
(bus) — 2020/H 1 2021 1)

Term

Million
bus km
p. a.

thereof
versus
H 1 2020

 

Czech Republic

Pilsen Region South

06/2020—06/2030

10.0

+4.2

Czech Republic

Pilsen Region North

03/2020—03/2030

8.2

+1.4

Sweden

Kristianstad

12/2020—12/2023

3.5

+1.8

Slovakia

City of Trnava

06/2021—05/2031

1.2

+0.1

Total 2)

  

22.9

+7.5

1) Services were previously not provided by DB Arriva.
2) Differences due to rounding are possible.

Major contract cessations

Major contract cessations

(bus) — 2020/H 1 2021 1)

Cessation

Million
bus km
p. a.

thereof
versus
H 1 2020

 

Sweden

Halland South
(Halmstad City)

06/2020

5.9

–2.5

Czech Republic

Královéhradecký
region

02/2021

6.9

–2.9

Denmark

Movia A18

06/2021

5.0

–0.4

Total 2)

  

17.8

–5.8

1) Services were previously provided by DB Arriva.
2) Differences due to rounding are possible.

Order book

Order book ( € billion)

Jun 30,
2021

Dec 31,
2020

Change

absolute

%

 

DB Arriva

13.2

14.4

–1.2

–8.3

     secured

9.4

10.2

–0.8

–7.8

     unsecured

3.8

4.2

–0.4

–9.5

Revenues that are directly connected with transport contracts or concessions are either independent of (secured revenues, primarily concession fees) or dependent on (unsecured revenues, primarily revenues from fares) the number of passengers.

Overall, in the first half of 2021 the order book declined. The additions from transport contracts awarded of about € 0.4 ­
billion were offset by disposals of about € 1.7 billion, mainly as a result of services rendered. Changes in assumptions of about € 0.1 billion have a positive impact.

Where would you most likely position yourself?Thank you for your feedback!